Amgen, Inc.

Bionext

Project Overview

The Amgen BioNext Project introduced a large-scale manufacturing facility for human therapeutics production, including upstream and downstream processing, to the company’s West Greenwich, RI campus.

Project Specifications

Contract Amount: $36,000,000

Total Project Value: $500,000,000

Construction Manager: Fluor Construction

Architect/Mechanical Engineer:

Aker Solutions

Facility Size: 450,000 SF

Project Location: West Greenwich, RI

Download Case Study (PDF)

Services Provided

New Construction

Clean / High Purity

Process / Utility Piping

Fabrication

Highlights / Achievements

384,000 SF new production, production support and warehouse buildings

47,000 SF Central Utility Building Addition on Existing Building

Fast-Track Schedule with 33 months between Conceptual Design and Mechanical Completion

Building Information Modeling

Off-site Piping Prefabrication for Entire Project

New Water Treatment Area, Boilers, and Chillers

Careful Phasing to tie-in to Existing Services

Minimal Disruption to Operating 24/7 Production Lines

Value Delivered

Arden exceeded demanding deadlines by prefabricating all piping for the project offsite. Teams worked extended hours during the installation and commissioning phases of work to shave additional time off the schedule. Due in part to these efforts, the project was completed nearly 3 months ahead of target.